For UK clients and contractors seeking lifting plans or lift-operation support. Share the work, outcome and known information; open details can follow.

01 / Prepare an enquiry

What to include in your first brief.

For each detail, say whether it is confirmed, estimated, assumed or unknown, and give its source, date or drawing revision where available. These labels describe what you supplied; a detail or record is not independently verified just because it appears in an enquiry. Do not guess missing values. State what is unknown and what may need checking: gaps do not prevent an initial enquiry.

01 / Enquiry information

Work scope and intended outcome

Set out the task and what the project needs to achieve.

  • What work is in scope, why the lift is needed and the intended outcome, including items attached, removed or moved.
  • The proposed sequence, number or frequency of lifts, and any work that must happen before or after them.
  • Whether you are asking about a professional lifting plan, lift-operation support, or both, and the project decision or deliverable you are seeking.
  • Relevant project requirements, site rules, work limits and interfaces already known to your team.

02 / Enquiry information

Load and supporting information

Describe the load and identify where its details came from.

  • Load description, weight and units, plus the source and date of the information, such as a drawing, manufacturer record or weigh record.
  • Dimensions, intended orientation and any known centre-of-gravity information, including the drawing reference or measurement basis where available.
  • Lifting-point positions, proposed connection details and available design, rating or inspection information.
  • Available load drawings, lifting-point details, equipment information or other records; identify revisions and describe anything not yet available.

03 / Enquiry information

Proposed equipment and rigging

Share the equipment identity and configuration being considered, if known.

  • Proposed crane or other lifting equipment, with make, model or asset identity and the planned configuration where available.
  • Available load-chart details for the proposed configuration, including relevant radius, boom or jib arrangement and any stated capacity limits.
  • Proposed slings, lifting accessories, beams or other rigging, with arrangement information and available ratings or examination records.
  • Equipment condition, alternative equipment or any chart, rating, examination or lifting-point information still to be confirmed.

04 / Enquiry information

Site, route and interfaces

Give the location and describe the route and conditions that may affect the lift.

  • Site location, access and working space for the lifting equipment, load and people.
  • Known ground and supporting-structure conditions, available capacity or survey evidence, and any proposed mats or crane pads.
  • Proposed crane position, pick and landing points, load path, working radius, clearances and any intermediate positions.
  • Known overhead or buried services, structures, pits or trenches, obstructions, traffic, public areas, infrastructure and other work.
  • Available site surveys, utility or service records, ground information and site rules; label records as current, dated or still to be checked.

05 / Enquiry information

People and timing

Share the proposed sequence and who is expected to take part.

  • Known planning, supervisory and lifting-team roles, relevant competence information, responsibilities and communication arrangements.
  • Requested date or time window, work duration and programme, access or permit constraints.
  • Environmental constraints known to the project, such as weather exposure, wind limits set by the responsible process, visibility or lighting.

This is a preparation checklist, not a universal statutory form. What is needed depends on the particular operation, its foreseeable risks and complexity.

02 / UK legal and HSE sources

Planning remains a competent-person task.

This is a preparation checklist, not a universal statutory form. What is needed depends on the particular operation, its foreseeable risks and complexity.

Under LOLER 1998 regulation 8 (opens in a new tab), an employer must ensure that every lifting operation involving lifting equipment is properly planned by a competent person, appropriately supervised and carried out safely. The HSE LOLER overview (opens in a new tab) summarises these duties.

HSE planning guidance says the plan should address foreseeable risks and identify the resources needed, including people. The degree of planning and the detail of the plan should be proportionate to the foreseeable risks. For much more complex operations, such as a tandem lift using multiple cranes, HSE says a written plan should be developed by someone with significant and specific competence suited to the task. See HSE guidance on planning and organising lifting operations (opens in a new tab).

More detailed advice appears in HSE L113, Safe use of lifting equipment (opens in a new tab), the Approved Code of Practice and guidance for LOLER. LOLER is binding legislation; HSE webpage guidance is non-compulsory advice unless stated otherwise. L113 is an Approved Code of Practice and guidance: it is not legislation, but HSE explains that an ACOP has a special legal status. This guide does not cite a British Standard or replace legal duties or any standard specified for a project. See HSE’s explanation of the legal status of guidance and ACOPs (opens in a new tab).

03 / Project-specific review

What needs project-specific assessment

An enquiry guide can help organise information, but it cannot establish whether a proposed lift is safe or suitable. A competent person needs to assess the actual operation, evidence and conditions for the project.

  • Ground and supporting-structure capacity, support reactions and the suitability of mats or crane pads.
  • Buried services, pits, trenches, obstructions and the verified position of plant or infrastructure near the lift.
  • Equipment condition and configuration, available capacity information, load balance and the effects of rigging.
  • Proximity to overhead lines, structures and other work, together with access, clearances and the load path.
  • Environmental conditions and other foreseeable risks, and the people, resources, supervision and controls needed for the operation.

If actual conditions or parameters differ from the lift plan, refer the change through the responsible competent person and the project’s review process before proceeding. Do not adapt a plan ad hoc; this guide does not give lift instructions or authorise work.

04 / Consultancy enquiry

Discuss the lift and its constraints

Professional lifting plans and operations support

Varentius supports the lifting lifecycle from planning and technical assessment through lift methodology to on-site execution and operational support. The founder, Damien Proudlove, has more than 20 years' experience across construction sectors ranging from civils, overhead-line electrification (OLE) and rail to oil and gas, including lifting operations and engineering design and installation.

Experience includes work associated with Network Rail; this describes project experience and is not an endorsement by Network Rail.

Varentius consultancy is scoped and quoted through a project enquiry. The lift-planning and RAMS product is in development. Software access and consultancy are separate routes; a software subscription does not include consultant hours, attendance or a Varentius-signed plan. Use the product page for software information, not to request project consultancy. Company-licence information.